Perbandingan Produktivitas Pemancangan Steel Sheet Pile Menggunakan Silent Piler (Crush Mode) Dan Kombinasi Preboring Dengan Vibro Hammer
Dwiyanti Roihatul Jannah, Dr. Eng. Wakhidatik Nurfaida, S.T., M.Eng.
2026 | Tugas Akhir | D4 TEKNIK PENGELOLAAN DAN PEMELIHARAAN INFRASTRUKTUR SIPIL
Pemancangan Steel Sheet Pile (SSP)
umumnya menggunakan metode vibro hammer yang menghasilkan getaran
yang tinggi yang berpotensi berdampak terhadap bangunan sekitar. Salah satu
proyek yang menggunakan metode tersebut adalah JSDP zona 1 paket 3. Pada
shaft C-22.0 yang berdekatan dengan sekolah dan bangunan cagar budaya,
pemancangan dengan vibro hammer dihentikan karena mengganggu kegiatan
belajar dan menimbulkan retakan. Olah karena itu, kontraktor beralih ke silent piler (crush
mode). Pemilihan metode pemancangan perlu mempertimbangkan dampak getaran
selain produktivitas dan biaya dan dampak getaran terhadap bangunan sekitar
(SNI 7571:2010; Kepmen LH No. 49 Tahun 1996) Penelitian ini bertujuan membandingkan silent piler (crush mode) dan
kombinasi preboring dengan vibro hammer berdasarkan
produktivitas, biaya pelaksanaan, dampak getaran dan menentukan metode yang
paling efektif.
Penelitian ini dilakukan pada shaft C-22.0
yang menggunakan metode silent piler crush mode dan E-12.0 yang menggunakan
kombinasi preboring dengan vibro hammer. Data waktu siklus dan
getaran diperoleh melalui pengamatan langsung mengunakan stopwatch dan vibration
meter. Data biaya diperoleh dari data proyek. Analisis produktivitas
dilakukan berdasarkan waktu siklus pemancangan, biaya dibandingkan per meter,
dan dampak getaran dianalisis berdasarkan nilai Peak Particle Velocity (PPV)
dengan ambang batas 2 mm/s sesuai Keputusan Menteri Negara Lingkungan Hidup
Nomor 49 Tahun 1996 dan SNI 7571:2010.
Berdasarkan hasil penelitian,
metode Silent Piler (Crush Mode) merupakan metode yang lebih efektif dan
efisien untuk pekerjaan pemancangan SSP pada lokasi penelitian yang berdekatan
dengan bangunan sensitif. Metode ini menghasilkan produktivitas sebesar 0,55
m/menit dengan biaya Rp689.603,65 per meter, sedangkan metode preboring dengan
Vibro Hammer menghasilkan produktivitas sebesar 0,30 m/menit dengan biaya
Rp1.268.703,57 per meter. Hasil pengukuran getaran menunjukkan bahwa Silent
Piler menghasilkan PPV sebesar 0,32–1,69 mm/s dan memenuhi ambang batas 2 mm/s,
sedangkan Vibro Hammer menghasilkan PPV sebesar 1,48–6,20 mm/s, dengan sebagian
besar titik pengukuran melebihi ambang batas tersebut. Namun, metode preboring
dengan Vibro Hammer tetap dapat menjadi alternatif karena ketersediaan alat dan
tenaga kerja yang relatif lebih mudah ditemukan di lapangan.
The installation of steel sheet piles (SSP) generally uses
the vibro hammer method, which generates high levels of vibration and may
affect surrounding buildings. One project employing this method is the Jakarta
Sewerage Development Project (JSDP) Zone 1 Package 3. At Shaft C-22.0, located
near a school and a cultural heritage building, vibro hammer installation was
halted because it disrupted learning activities and cracks were observed in
nearby buildings. Consequently, the contractor switched to the Silent Piler
(Crush Mode) method. The selection of an SSP installation method needs to
consider the vibration impacts on surrounding buildings in addition to
productivity and cost (SNI 7571:2010; Minister of Environment Decree No. 49 of
1996). This study aims to compare the Silent Piler (Crush Mode) method with the
combination of preboring and vibro hammer in terms of productivity,
implementation cost, and vibration impacts, and to determine which method is
more effective.
The study was conducted at Shaft C-22.0, where the Silent
Piler (Crush Mode) method was used, and Shaft E-12.0, where the combination of
preboring and vibro hammer was applied. The cycle time and vibration data were
obtained through direct field observations using a stopwatch and a vibration
meter, while the cost data were obtained from project records. Productivity was
analyzed based on pile installation cycle times, costs were compared per meter,
and the vibration impacts were evaluated using peak particle velocity (PPV),
with a threshold of 2 mm/s based on Minister of Environment Decree No. 49 of
1996 and SNI 7571:2010.
Based on the research findings, the Silent Piler (Crush
Mode) method is more effective and efficient for SSP installation at the study
location, which is adjacent to vibration-sensitive buildings. This method
achieved a productivity of 0.55 m/min at a cost of IDR 689,603.65 per meter,
whereas the combination of preboring and vibro hammer achieved a productivity
of 0.30 m/min at a cost of IDR 1,268,703.57 per meter. The vibration
measurements showed that the Silent Piler generated PPV values ranging from 0.32
to 1.69 mm/s, meeting the 2 mm/s threshold. In contrast, the vibro hammer
generated PPV values ranging from 1.48 to 6.20 mm/s, with most measurement
points exceeding the threshold. However, the combination of preboring and vibro
hammer remains a viable alternative because the required equipment and skilled
labor are relatively more readily available in the field.
Kata Kunci : steel sheet piles, silent piler, vibro hammer, productivity, vibration.