Analisis Strategi Operasi Melalui Integrasi House of Risk dan Green Lean Six Sigma: Studi Kasus Proyek Jalan Tol Solo-Yogyakarta-NYIA
Muhammad faiz irsyad, Nofie Iman Vidya Kemal, M.Sc., Ph.D.,
2026 | Tesis | S2 Manajemen
Penelitian ini bertujuan
menganalisis strategi operasi melalui integrasi House of Risk (HOR) dan Green
Lean Six Sigma (GLSS) pada Proyek Jalan Tol Solo-Yogyakarta-NYIA, khususnya
Seksi 2 Paket 2.2. Fokus penelitian diarahkan pada pekerjaan tanah, beton, dan
baja untuk mengevaluasi mutu, pemborosan proses, estimasi emisi akibat kondisi idle,
serta profil risiko operasional proyek. Penelitian menggunakan desain studi
kasus dengan integrasi analisis kuantitatif deskriptif dan analisis kualitatif.
Data diperoleh melalui penelaahan dokumen pengendalian mutu, observasi proses,
wawancara semi-terstruktur, kuesioner validasi ahli, dan diskusi validasi
tindakan mitigasi. Pengukuran Six Sigma dilakukan terhadap 600 unit
inspeksi beton, 979 unit inspeksi baja, dan 703 unit inspeksi tanah. Hasil
pengukuran menunjukkan bahwa pekerjaan baja memiliki nilai sigma tertinggi
sebesar 4,43, diikuti beton sebesar 4,16, dan tanah sebesar 4,09. Berdasarkan snapshot
Value Stream Mapping, pekerjaan baja memiliki Process Cycle Efficiency
sebesar 87,50 persen, beton sebesar 81,25 persen, dan tanah sebesar 76,92
persen. Pada observasi lapangan pekerjaan tanah tercatat waktu tunggu selama 45
menit dengan estimasi emisi idle sebesar 5,36 kg CO2e per truk. Nilai
emisi baja tidak dibandingkan secara langsung dengan beton dan tanah karena
menggunakan unit pelaporan berbeda, yaitu per siklus alat internal. Analisis
HOR Fase 1 mengidentifikasi empat agen risiko prioritas, yaitu rendahnya
konsistensi kepatuhan pekerja terhadap SOP, fluktuasi cuaca ekstrem, kemacetan
rute distribusi, dan ketidakseimbangan kapasitas alat berat. Pada HOR Fase 2,
tindakan mitigasi dengan prioritas tertinggi adalah implementasi Visual Poka-Yoke dan Behavior-Based Quality
Control, diikuti penerapan Service Level Agreement berbasis
indikator kinerja bagi subkontraktor. Hasil penelitian memberikan dasar
terstruktur bagi perusahaan untuk menentukan prioritas perbaikan mutu,
efisiensi, risiko, dan keberlanjutan operasional.
This study analyzes operations
strategy through the integration of House of Risk (HOR) and Green Lean Six
Sigma (GLSS) in the Solo-Yogyakarta-NYIA Toll Road Project, specifically
Section 2 Package 2.2. The analysis focuses on soil, concrete, and steel work
to evaluate quality performance, process waste, estimated emissions from idle
conditions, and the operational risk profile. The study applies a case study
design that integrates descriptive quantitative analysis and qualitative
analysis. Data were obtained from quality control documents, process
observations, semi-structured interviews, expert validation questionnaires, and
a mitigation action validation discussion. The Six Sigma assessment was
conducted using 600 concrete inspection units, 979 steel inspection units, and
703 soil inspection units. The results show that steel work achieved the
highest sigma level at 4.43, followed by concrete at 4.16 and soil at 4.09.
Based on a Value Stream Mapping snapshot, steel work achieved a Process Cycle
Efficiency of 87.50 percent, concrete achieved 81.25 percent, and soil work
achieved 76.92 percent. During the observed soil work episode, a waiting time
of 45 minutes was recorded, resulting in an estimated idle emission of 5.36 kg
CO2e per truck. The steel emission estimate was not directly compared with
those of concrete and soil because it used a different reporting unit based on
an internal equipment cycle. HOR Phase 1 identified four priority risk agents,
namely inconsistent worker compliance with standard operating procedures,
extreme weather fluctuations, traffic congestion along distribution routes, and
imbalance in heavy equipment capacity. HOR Phase 2 identified the
implementation of Visual Poka-Yoke and Behavior-Based Quality Control as the
highest- priority mitigation action, followed by the implementation of
performance- based Service Level Agreements for subcontractors. The findings
provide a structured basis for prioritizing quality, efficiency, risk, and
operational sustainability improvements.
Kata Kunci : House of Risk, Green Lean Six Sigma, Strategi Operasi, Manajemen Risiko, Proyek Jalan Tol, Keberlanjutan