Analisis Dampak Integrasi Pembangkit Listrik Tenaga Bayu Mempertimbangkan Stabilitas Tegangan dan Keandalan Sistem Kelistrikan 150 kV Yogyakarta
Ariska Meyny Ningrum, Ir. Ahmad Adhiim Muthahhari, S.T., M.Eng., IPM
2026 | Tugas Akhir | D4 TEKNOLOGI REKAYASA ELEKTRO
Pengembangan
Energi Baru Terbarukan (EBT) terus ditingkatkan untuk mendukung transisi energi
nasional. Salah satu rencana pengembangannya tercantum dalam Rencana Usaha
Penyediaan Tenaga Listrik (RUPTL) 2025–2034, yaitu pembangunan Pembangkit
Listrik Tenaga Bayu (PLTB) di Yogyakarta. Integrasi PLTB ke dalam sistem
transmisi 150 kV Yogyakarta berpotensi memengaruhi kondisi operasi sehingga
diperlukan kajian terhadap stabilitas tegangan dan keandalan sistem pada
kondisi normal maupun kontingensi. Penelitian ini bertujuan menganalisis
pengaruh integrasi PLTB terhadap kondisi operasi dan keandalan sistem transmisi
150 kV Yogyakarta. Identifikasi lokasi potensial dilakukan menggunakan data
Global Wind Atlas (GWA) dan NASA POWER yang dinormalisasi berdasarkan nilai
maksimum. Hasil analisis menunjukkan bahwa Kalasan, Semanu, Ponjong, dan
Girijati memiliki kecepatan angin 6,23–6,83 m/s pada ketinggian hub 97,5 m
sehingga dipilih sebagai lokasi pengembangan PLTB. Simulasi dilakukan
menggunakan DIgSILENT PowerFactory 2024 dengan kapasitas PLTB 50 MW, 250 MW,
350 MW, dan 450 MW. Analisis meliputi aliran daya, kurva P–V, simulasi
kontingensi lepasnya Interbus Transformer (IBT) Pedan 1 dan Pedan 2 serta IBT
Pedan 3 dan Pedan 4. Pelepasan beban ditentukan menggunakan Optimal Power Flow
(OPF), sedangkan keandalan sistem dievaluasi menggunakan indeks Energy Not
Supplied (ENS), Energy Saved (ES), dan Expected Energy Not Supplied (EENS).
Hasil penelitian menunjukkan bahwa pada skenario PLTB 450 MW, tegangan terendah
meningkat dari 0,938 p.u. menjadi 0,974 p.u., pembebanan saluran
Sanggrahan–Medari menurun dari 83,1% menjadi 69,2%, rugi-rugi daya berkurang
dari 21.345 kW menjadi 13.356,3 kW, dan daya kritis meningkat dari 1153,36 MW
menjadi 1273,39 MW. Pada kondisi kontingensi, ENS akibat lepasnya IBT Pedan 1
dan Pedan 2 menurun dari 33.060,28 MWh menjadi 0 MWh, sedangkan akibat lepasnya
IBT Pedan 3 dan Pedan 4 menurun dari 23.624,13 MWh menjadi 1.672,21 MWh. Hasil
tersebut menunjukkan bahwa integrasi PLTB mampu meningkatkan kondisi operasi,
stabilitas tegangan, dan keandalan sistem transmisi 150 kV Yogyakarta.
The
development of New and Renewable Energy (NRE) continues to be promoted to
support Indonesia’s national energy transition. One of the planned developments
is outlined in the 2025–2034 Electricity Supply Business Plan (RUPTL), which
includes the construction of a Wind Power Plant (PLTB) in Yogyakarta. The
integration of the wind power plant into the 150 kV Yogyakarta transmission
system has the potential to affect system operating conditions, requiring an
assessment of voltage stability and system reliability under both normal and
contingency conditions. This study aims to analyze the impact of wind power
integration on the operating conditions and reliability of the 150 kV
Yogyakarta transmission system. Potential site identification was conducted
using Global Wind Atlas (GWA) and NASA POWER data normalized based on the
maximum value. The results indicate that Kalasan, Semanu, Ponjong, and Girijati
have wind speeds ranging from 6.23 to 6.83 m/s at a hub height of 97.5 m and
were therefore selected as potential wind farm locations. Simulations were
performed using DIgSILENT PowerFactory 2024 with installed wind power
capacities of 50 MW, 250 MW, 350 MW, and 450 MW. The analysis included power
flow, P–V curve, and contingency simulations involving the outage of Pedan IBT
1 and 2 as well as Pedan IBT 3 and 4. Load shedding was determined using the
Optimal Power Flow (OPF) method, while system reliability was evaluated using
the Energy Not Supplied (ENS), Energy Saved (ES), and Expected Energy Not
Supplied (EENS) indices. The results show that, under the 450 MW wind power scenario,
the minimum system voltage increased from 0.938 p.u. to 0.974 p.u., the loading
of the Sanggrahan–Medari transmission line decreased from 83.1% to 69.2%, power
losses were reduced from 21,345 kW to 13,356.3 kW, and the critical loading
increased from 1153.36 MW to 1273.39 MW. Under contingency conditions, ENS due
to the outage of Pedan IBT 1 and 2 decreased from 33,060.28 MWh to 0 MWh, while
ENS due to the outage of Pedan IBT 3 and 4 decreased from 23,624.13 MWh to
1,672.21 MWh. These results demonstrate that wind power integration improves
system operating conditions, voltage stability, and the reliability of the 150
kV Yogyakarta transmission system.
Kata Kunci : PLTB, aliran daya, stabilitas tegangan, kontingensi, keandalan sistem