Analisis Perbandingan Metode Open Cut dan Sheet Pile pada Penggantian Saluran Outfall di Bawah Jalan Lintas Sumatera
Darren Halim, Dr. Eng. Ir. Fikri Faris, S.T., M.Eng., IPM.
2026 | Skripsi | TEKNIK SIPIL
Pekerjaan penggantian saluran outfall pada area
crossing Jalan Lintas Sumatera memiliki tantangan teknis karena berada
di bawah badan jalan nasional dan memerlukan galian sedalam 6,34 m pada segmen
sepanjang 9,50 m. Saluran eksisting berupa corrugated steel pipe (CSP)
lama direncanakan diganti dengan box culvert baru. Perancangan ini
bertujuan membandingkan metode open cut dan sheet pile
berdasarkan kestabilan geoteknik, kuantitas pekerjaan, dan durasi pelaksanaan.
Analisis kestabilan kedua metode
dilakukan menggunakan GEO5 dengan metode Morgenstern-Price. Kuantitas pekerjaan
dihitung berdasarkan geometri masing-masing metode, sedangkan durasi
pelaksanaan dihitung berdasarkan kuantitas pekerjaan, produktivitas alat,
jumlah alat, dan urutan pekerjaan.
Hasil analisis menunjukkan kedua
metode memenuhi kriteria kestabilan geoteknik. Metode open cut terpilih
dengan kemiringan lereng 3:2 menghasilkan faktor keamanan 1,32 (kriteria
minimum 1,3), sedangkan sheet
pile menghasilkan faktor keamanan struktur 2,15 menggunakan tipe
ESC-CRZ52-700 dengan kedalaman minimum 6,86 m. Dari aspek kuantitas, open
cut menghasilkan pekerjaan berbasis volume 4.762,63 m³, luas 613,04 m², dan
unit sebanyak 11 unit, sedangkan sheet pile menghasilkan volume 2.725,02
m³, luas 256,32 m², panjang 784 m (pemancangan 392 m dan pencabutan 392 m), dan
unit 11 unit. Dari aspek durasi, open cut membutuhkan 7,25 hari
sedangkan sheet pile membutuhkan 16,89 hari. Dengan demikian, metode open
cut dipilih sebagai metode yang lebih sesuai karena memenuhi kriteria
kestabilan, berdurasi lebih singkat, dan memenuhi target maksimum 14 hari,
sedangkan sheet pile tidak memenuhi target tersebut.
The replacement of the
outfall channel at the crossing area of Jalan Lintas Sumatera presents
technical challenges due to its location beneath a national road, requiring a
6.34 m deep excavation along a 9.50 m work segment. The existing corrugated
steel pipe (CSP) channel is planned to be replaced with a new box culvert. This
study aims to compare the open cut and sheet pile methods based on geotechnical
stability, work quantity, and construction duration.
The stability analysis
of both methods was conducted using GEO5 with the Morgenstern-Price method.
Work quantities were calculated based on the geometry of each method, while
construction duration was estimated from work quantities, equipment productivity,
number of equipment units, and work sequence.
The results show that
both methods satisfy the geotechnical stability criteria. The selected open cut
method, with a 3:2 slope inclination, produced a factor of safety of 1.32
(minimum criterion of 1.3), while the sheet pile method produced a system
factor of safety of 2.15 using ESC-CRZ52-700 sheet piles with a minimum
embedment depth of 6.86 m. In terms of work
quantity, the open cut method resulted in 4,762.63 m³ of volume-based work,
613.04 m² of area-based work, and 11 units, while the
sheet pile method resulted in 2,725.02 m³ of volume, 256.32 m² of area, 784 m
of length (392 m of driving and 392 m of extraction), and 11 units. In terms of duration, the open cut method required
7.25 days, while the sheet pile method required 16.89 days. Therefore, the open
cut method was selected as the more suitable method, satisfying the stability
criteria, requiring a shorter duration, and meeting the 14-day maximum target,
while the sheet pile method did not meet this target.
Kata Kunci : open cut, sheet pile, corrugated steel pipe, stabilitas lereng galian, durasi pelaksanaan