ANALISIS VOLUME BETON BERDASARKAN METODE KONVENSIONAL DAN BIM SERTA PENYEBAB PERBEDAAN HITUNGAN DENGAN PENDEKATAN MIXED METHODS Studi Kasus Pembangunan SD Negeri Joglo Surakarta
Alvin Hannan Jusuf Prabowo, Dr. Toriq Arif Ghuzdewan, S.T., M.Sc.E.
2026 | Skripsi | TEKNIK SIPIL
Ketepatan perhitungan volume beton merupakan faktor penentu keandalan estimasi biaya
pekerjaan struktur pada proyek gedung. Metode konvensional berbasis gambar kerja 2D rentan
terhadap inkonsistensi aturan ukur dan kesalahan rekapitulasi, sementara metode Building
Information Modeling (BIM) berpotensi meningkatkan akurasi kuantitas melalui ekstraksi
langsung dari model 3D. Namun, perbandingan kedua metode yang sekaligus mengukur selisih
volume, dampak biaya, dan faktor penyebab selisih dalam satu kerangka analisis yang utuh
masih terbatas, terutama pada konteks proyek gedung di Indonesia. Penelitian ini bertujuan
menganalisis perbedaan volume beton hasil quantity take-off (QTO) antara metode
konvensional dan BIM, menilai dampaknya terhadap estimasi biaya, serta mengidentifikasi
faktor penyebab selisih berdasarkan perspektif pelaku proyek.Hasil penelitian ini diharapkan
memberi gambaran nyata bagi praktisi konstruksi mengenai implikasi pemilihan metode QTO
terhadap akurasi estimasi biaya.
Penelitian menggunakan studi kasus Proyek Pembangunan Gedung SD Negeri Joglo Surakarta
dengan objek analisis elemen beton struktural meliputi kolom, balok, dan pelat. Desain
penelitian menggunakan explanatory sequential mixed methods, yang dilaksanakan dalam dua
tahap berurutan. Tahap pertama adalah analisis kuantitatif, yaitu perhitungan volume beton
metode konvensional berbasis gambar kerja 2D menggunakan Microsoft Excel, pemodelan
BIM menggunakan Autodesk Revit, dan ekstraksi volume melalui material takeoff schedule.
Selisih volume dan dampak biaya dihitung per elemen menggunakan harga satuan beton ready
mix fc'25 MPa. Tahap kedua adalah analisis kualitatif, yaitu wawancara semi-terstruktur
dengan dua Quantity Surveyor proyek yang dipilih berdasarkan temuan kuantitatif, diikuti
analisis tematik untuk menyusun tema penyebab selisih. Kedua tahap diintegrasikan melalui
joint display.
Total volume konvensional sebesar 754,06 ????3 dan volume BIM sebesar 745,91 ????3
menghasilkan selisih total ?V = 8,15 ????3 (1,09%). Selisih total yang kecil ini bersifat
menyesatkan karena merupakan hasil kompensasi parsial antara overestimate besar pada Pelat
Lantai Struktural (?V = +41,86 ????3, +21,83%) dan underestimate kumulatif pada seluruh
elemen balok, dengan selisih tertinggi ?37,35% pada Balok Anak BA1. Selisih biaya total
sebesar Rp 6.539.764 (1,08%), dengan Pelat Lantai Struktural menyumbang selisih biaya
terbesar sebesar Rp 33.589.511. Dari wawancara diperoleh tujuh tema penyebab selisih (T1
T7), dengan T1 (prinsip gross vs net pada pelat) dan T7 (pengurangan tinggi penampang balok
sebesar tebal pelat secara menyeluruh) sebagai penyebab dominan. Penelitian ini membuktikan
bahwa selisih QTO bersifat sistematis, tidak dapat dideteksi hanya dari angka total, dan BIM
menghasilkan volume yang lebih akurat secara geometris pada level elemen individual.
Penelitian ini memberi dasar bagi praktisi dan peneliti untuk menerapkan protokol QTO
berbasis BIM yang lebih terstandar pada proyek gedung di Indonesia.
Accurate concrete volume calculation is a key determinant of cost estimation reliability in
building construction projects. The conventional method based on 2D working drawings is
prone to measurement rule inconsistencies and recapitulation errors, while the Building
Information Modeling (BIM) method offers potential improvements in quantity accuracy
through direct extraction from a 3D model. However, comparative studies that simultaneously
measure volume discrepancy, cost impact, and causative factors within a single analytical
framework remain limited, particularly in the context of building projects in Indonesia. This
study aims to analyze the difference in concrete volume from quantity take-off (QTO) between
the conventional and BIM methods, assess its impact on cost estimation, and identify the causes
of discrepancy from the perspective of project practitioners. The findings are expected to
provide practical insights for construction professionals regarding the implications of QTO
method selection on cost estimation accuracy.
The study uses the SD Negeri Joglo Surakarta Building Construction Project as a case study,
with the analysis limited to structural concrete elements comprising columns, beams, and slabs.
The study employs an explanatory sequential mixed methods design, executed in two sequential
phases. The first phase is quantitative analysis, consisting of conventional concrete volume
calculation based on 2D working drawings using Microsoft Excel, BIM modeling using
Autodesk Revit, and volume extraction through the material takeoff schedule. Volume
discrepancies and cost impacts were calculated per element using the unit price of ready-mix
concrete fc'25 MPa. The second phase is qualitative analysis, consisting of semi-structured
interviews with two project Quantity Surveyors selected based on the quantitative findings,
followed by thematic analysis to construct themes explaining the causes of discrepancy. Both
phases were integrated through a joint display.
Total conventional volume of 754.06 ????3 and BIM volume of 745.91 ????3 yield a total
discrepancy of ?V = 8.15 ????3 (1.09%). This small total discrepancy is misleading because it
results from partial compensation between a large overestimate on the Structural Floor Slab
(?V = +41.86 m³, +21.83%) and a cumulative underestimate across all beam elements, with
the highest discrepancy of ?37.35% on Child Beam BA1. The total cost discrepancy is Rp
6,539,764 (1.08%), with the Structural Floor Slab contributing the largest cost discrepancy of
Rp 33,589,511. From the interviews, seven themes were identified as causes of discrepancy
(T1–T7), with T1 (gross vs. net principle on slabs) and T7 (uniform reduction of beam cross
section height by slab thickness across all beam types) as the dominant causes. This study
proves that QTO discrepancies are systematic in nature, cannot be detected from total figures
alone, and that BIM produces geometrically more accurate volumes at the individual element
level. These findings provide a basis for practitioners and research
Kata Kunci : BIM, Autodesk Revit, volume beton, quantity take-off, perbedaan kuantitas, estimasi biaya, proyek gedung