DESAIN AWAL PLTS TERAPUNG BERDASARKAN KARAKTERISTIK SUNGAI MUSI

Muhammad Dimas Firdaus, Dr. Ir. Rachmawan Budiarto, S.T., M.T., IPU ; Roni Irnawan S.T., M.Sc, Ph.D

2026 | Tesis | MAGISTER TEKNIK FISIKA

Peningkatan kebutuhan energi listrik di Indonesia mendorong pemanfaatan energi baru terbarukan untuk mengurangi ketergantungan pada bahan bakar fosil. Energi surya menjadi salah satu sumber energi potensial, namun pengembangan PLTS berbasis darat sering terkendala keterbatasan lahan. Salah satu alternatif yang berkembang adalah Pembangkit Listrik Tenaga Surya (PLTS) terapung. Penelitian ini bertujuan merancang desain awal PLTS terapung berdasarkan karakteristik Sungai Musi.

Metode penelitian meliputi pengumpulan data sekunder, analisis karakteristik lokasi, evaluasi gaya lingkungan, serta perancangan sistem penambatan dan pelampung. Perancangan dilakukan dengan tiga skenario okupansi area, yaitu ±20%, ±50%, dan ±90?ri luas efektif lokasi sebesar 50.000 m². Hasil penelitian menunjukkan bahwa Sungai Musi memiliki potensi yang baik untuk pengembangan PLTS terapung dengan kapasitas sistem sebesar 1,014 MWp, 2,106 MWp, dan 4,505 MWp. Beban horizontal terbesar terjadi akibat kombinasi gaya arus sungai dan gaya angin longitudinal searah aliran, dengan gaya total berturut-turut sebesar 361.716,42 N, 751.257,18 N, dan 1.613.811,72 N. Sistem penambatan hybrid berupa kombinasi tiang dan tali dinilai mampu menahan gaya lingkungan dan menjaga kestabilan struktur

Penelitian ini menyimpulkan bahwa desain awal PLTS terapung di Sungai Musi layak secara teknis untuk dikembangkan lebih lanjut dan dapat menjadi referensi awal bagi pengembangan PLTS terapung pada perairan sungai di Indonesia.

The increasing demand for electrical energy in Indonesia encourages the utilization of renewable energy sources to reduce dependence on fossil fuels. Solar energy is one of the most promising renewable energy sources; however, the development of land-based photovoltaic power plants is often constrained by limited land availability. One alternative that has gained significant attention is Floating Photovoltaic (FPV) systems. This research aims to design a preliminary floating photovoltaic system based on the characteristics of Sungai Musi.

The research method includes secondary data collection, site characteristic analysis, environmental load evaluation, and the design of mooring and floating systems. The design was carried out using three area occupancy scenarios, namely approximately ±20%, ±50%, and ±90% of the effective site area of 50,000 m². The results show that the Musi River has strong potential for floating photovoltaic development, with system capacities of 1.014 MWp, 2.106 MWp, and 4.505 MWp, respectively. The highest horizontal loading condition occurred due to the combination of river current force and longitudinal wind force in the flow direction, resulting in total forces of 361,716.42 N, 751,257.18 N, and 1,613,811.72 N, respectively. A hybrid mooring system combining piles and ropes was considered capable of resisting environmental loads and maintaining structural stability.

This study concludes that the preliminary floating photovoltaic design in the Musi River is technically feasible for further development and can serve as an initial reference for the development of floating photovoltaic systems in river waters in Indonesia.

Kata Kunci : PLTS terapung, Sungai Musi, gaya lingkungan, gaya angkat, gaya drag, sistem tambat, pelampung.