Optimasi Scheduling & Resource Leveling Proyek Konstruksi Dengan Time-Cost-Trade-Off Berbasis Genetic Algorithm Di Python
Didi Herianto Mahendra, Ir. Akhmad Aminullah, S.T., M.T., Ph.D.,IPU ; Dr. Toriq Arif Ghuzdewan, S.T., M.Sc.E
2025 | Tesis | S2 Teknik Sipil
Permasalahan
penjadwalan proyek konstruksi di Indonesia masih banyak dipengaruhi oleh
keterbatasan sumber daya, keterlambatan pelaksanaan, dan hubungan kompleks
antara waktu dan biaya (time-cost trade-off). Kondisi tersebut mendorong
perlunya pengembangan model optimasi yang mampu menghasilkan jadwal proyek
secara adaptif dan efisien, serta memenuhi seluruh aturan teknis dan regulasi
pemerintah. Tujuan utama penelitian ini adalah mengembangkan workflow hybrid
berbasis Critical Path Method (CPM) dan Genetic Algorithm (GA) yang terotomasi,
untuk membantu kontraktor dalam menentukan strategi percepatan proyek
menggunakan kombinasi pelaksanaan normal, lembur, dan subkontraktor, tanpa
menimbulkan pembengkakan biaya maupun pelanggaran batas regulasi lembur dan
subkontraktor.
Metode
penelitian yang digunakan melibatkan integrasi antara pemodelan jaringan kerja
proyek menggunakan CPM dan NetworkX dengan optimasi multi-mode penjadwalan
menggunakan Genetic Algorithm, diimplementasikan secara penuh dalam bahasa
pemrograman Python. Penelitian ini juga menetapkan parameter GA optimal,
menerapkan constraint percepatan hanya pada jalur kritis/near-kritis, serta
membatasi lembur maksimal 14 jam per minggu sesuai aturan pemerintah. Proses
validasi dilakukan melalui perhitungan manual, visualisasi Gantt chart, resource
histogram, serta ekspor hasil ke Excel dan Microsoft Project untuk menjamin
konsistensi dan kompatibilitas hasil.
Hasil penelitian menunjukkan bahwa workflow
hybrid CPM-GA yang dikembangkan mampu menurunkan total biaya proyek dari
Rp10.213.846.362 menjadi Rp9.857.885.763 (penurunan 3,49%) dan mempercepat
durasi dari 112 hari menjadi 73 hari (penurunan 34,82%). Model ini juga
menghasilkan distribusi mode optimal sebesar 46% aktivitas mode normal, 23%
lembur, dan 31% subkontraktor, serta mampu melakukan resource leveling
secara otomatis. Semua constraint dan regulasi utama terbukti terpenuhi tanpa
pelanggaran, sehingga model ini dapat dijadikan benchmark baru dan siap
diadopsi industri sebagai alat bantu pengambilan keputusan percepatan proyek
konstruksi yang efisien, akuntabel, dan sesuai regulasi nasional.
The
problem of construction project scheduling in Indonesia is often influenced by
resource limitations, implementation delays, and the complex relationship
between time and cost (time-cost trade-off). These conditions drive the need
for an optimization model capable of producing adaptive and efficient project
schedules while fulfilling all technical requirements and government
regulations. The main objective of this research is to develop an automated
hybrid workflow based on the Critical Path Method (CPM) and Genetic Algorithm
(GA), enabling contractors to determine project acceleration strategies through
a combination of normal execution, overtime, and subcontracting—without causing
excessive costs or violating overtime and subcontractor regulations.
The research methodology involves integrating
project network modeling using CPM and NetworkX with multi-mode scheduling
optimization via a Genetic Algorithm, fully implemented in Python. The study
establishes optimal GA parameters, enforces acceleration constraints only on
critical or near-critical paths, and limits overtime to a maximum of 14 hours
per week as required by Indonesian government policy. Validation processes
include manual calculations, Gantt chart visualizations, resource histograms,
and exporting results to Excel and Microsoft Project to ensure consistency and
output compatibility.
The results demonstrate that the developed hybrid CPM-GA workflow successfully reduces total project costs from IDR 10,213,846,362 to IDR 9,857,885,763 (a 3.49?crease) and shortens the project duration from 112 days to 73 days (a 34.82% reduction). The model also yields an optimal mode distribution of 46?tivities in normal mode, 23% in overtime, and 31% in subcontracting, while performing automatic resource leveling. All key constraints and regulations are strictly fulfilled without any violations, positioning this model as a new benchmark ready for adoption by the construction industry as an efficient, accountable, and regulation-compliant decision support tool for project acceleration
Kata Kunci : project scheduling, genetic algorithm, overtime, subcontractor, time-cost trade-off, government constraint, theory validation, cost efficiency, project acceleration, automated decision making