ANALISIS RISIKO KERUSAKAN RUMAH WARGA AKIBAT PENGARUH GETARAN PEMANCANGAN TIANG SPUNPILE DI PROYEK PEMBANGUNAN JALUR GANDA KERETA API SOLO-KADIPIRO
Annisa Rizky Nurfadillah, Ir. Rochmad Muryamto, M.Eng.Sc
2025 | Tugas Akhir | D4 TEKNOLOGI SURVEI DAN PEMETAAN DASAR
Pembangunan
infrastruktur jalur kereta api mampu memberikan dampak positif dalam
meningkatkan kesejahteraan rakyat dan menunjang pertumbuhan ekonomi. Dalam proses pemancangan tiang menggunakan Diesel
Hammer, pada kegiatan ini menimbulkan getaran di daerah sekitarnya dan
berpotensi merusak bangunan serta mengganggu aktifitas dan kenyamanan
masyarakat di sekitar lokasi pemancangan. Akibatnya terjadi kerusakan pada
beberapa rumah, membuat warga sekitar lokasi pemancangan merasa dirugikan dan
menuntut perkara ganti rugi. Untuk itu diperlukan
identifikasi area dan luas bangunan yang memiliki risiko kerusakan rumah pengaruh getaran
pemancangan tiang.
Proyek
akhir ini menggunakan metode analisa buffer dan calculate geometry dalam
geographic information system (GIS). Output proyek akhir ini
berupa informasi mengenai luasan bangunan rumah yang memiliki risiko kerusakan
rumah pengaruh getaran pemancangan spunpile di proyek pembangunan jalur
ganda kereta api Solo Balapan- Kadipiro. Pembuatan buffer dengan radius
zona 20 meter, 50 meter dan 100 meter. Pada zona tinggi memiliki jarak radius
yang dekat dan memiliki resiko kerusakan rumah yang tinggi, pada zona sedang memiliki jarak radius yang sedang dan
memiliki risiko kerusakan rumah sedang, dan pada zona rendah memiliki jarak
radius jauh dan memiliki resiko kerusakan rumah yang rendah.
Proyek
akhir ini menunjukkan bangunan yang saling bertampalan dengan zona radius lain.
Hal ini dikarenakan menggunakan metode multi ring buffer sehingga
terdapat area yang bertampalan satu sama lainnya. Luas area bangunan berisiko
terdampak pada radius 100 meter sebesar 20802 m2 dengan jumlah 313
bangunan, termasuk pada radius 20 meter sebesar 1360 m2 sebanyak 14
bangunan, dan pada radius 50 meter 7445 m2 sebanyak 107 bangunan.
The development of
railway infrastructure can have a positive impact on improving people's welfare
and supporting economic growth. In the process of pile driving using Diesel
Hammer, this pile driving activity causes vibrations in the surrounding area
and has the potential to damage buildings and disrupt the activities and
comfort of the community around the pile driving location. As a result, damage
occurred to several houses, making residents around the pile driving location
feel disadvantaged and demand compensation. For this reason, it is necessary to
identify the area and size of buildings that have a risk of house damage due to
vibrations from pile driving.
This final project uses
the buffer analysis method and calculate geometry in a geographic information
system (GIS). The output of this final project is information regarding the
area of ????houses affected by the risk of house damage due to vibrations from
spunpile pile driving in the Solo Balapan-Kadipiro double-track railway
construction project, precisely at KM 106 + 475 to KM 106 + 275. Making buffers
with a zone radius of 20 meters, 50 meters and 100 meters. In the high zone,
the radius distance is close and has a high risk of house damage, in the medium
zone, the radius distance is medium and has a moderate risk of house damage,
and in the low zone, the radius distance is far and has a low risk of house
damage.
This final project shows buildings that overlap with other radius zones. This is because it uses the multi ring buffer method so that there are areas that overlap each other. The area of ??the building at risk of being affected within a radius of 100 meters is 20802 m2 with a total of 313 buildings, including within a radius of 20 meters of 1360 m2 as many as 14 buildings, and within a radius of 50 meters 7445 m2 as many as 107 buildings. The building area data can be used as one of the reference data in the compensation or repair process if there is damage to the house building caused by the spunpile pile driving activity on the railway construction project.
Kata Kunci : getaran, infrastruktur, jalur kereta api, kerusakan bangunan rumah, pemancangan spunpile.