Analisis Risiko Pada Pelaksanaan Pekerjaan Bekisting Dengan Metode Job Safety Analysis (JSA) dan Hazard Identification Risk Assessment And Determining Control (HIRADC) Pada Proyek Rumah Susun Tenaga Pendidik UGM
Adrian Rafli Fahrezi, Ir. Fathi Basewed, M.T.
2023 | Tugas Akhir | D4 TEKNIK PENGELOLAAN DAN PEMELIHARAAN INFRASTRUKTUR SIPIL
Dalam
dunia konstruksi, bekisting berperan penting membentuk beton sesuai desain
sebelum mengeras, melibatkan instalasi, fabrikasi, dan pembongkaran. Risiko
dalam proses ini perlu dikelola. Tujuan penelitian ini ialah mengkaji
efektivitas metode Job Safety Analysis
(JSA) dan Hazard Identification Risk Assessment and Determining Control
(HIRADC) dalam pengendalian risiko pekerjaan bekisting pada proyek rumah susun
tenaga pendidik UGM.. Penelitian berfokus pada proyek rumah susun tenaga
pendidik UGM, bertujuan memahami kontribusi metode-metode tersebut dalam
mengurangi risiko dan meningkatkan keamanan pekerjaan. Hasilnya diharapkan
bermanfaat bagi industri konstruksi dan keselamatan, memberikan wawasan baru
dalam mengidentifikasi, menilai, dan mengendalikan risiko bekisting, juga meningkatkan
kesadaran akan keselamatan di kalangan tenaga pendidik dan praktisi, berpotensi
mengurangi insiden di proyek konstruksi mendatang.
Metode
penelitian ini menggunakan metode Job Safety Analysis (JSA) dan Hazard
Identification, Risk Assessment, and Determining Control (HIRADC) dalam
mengidentifikasi, dan mengevaluasi risiko pekerjaan yang terjadi pada pekerjaan
bekisting dan perancah di proyek Rumah Susun Tenaga Pendidik UGM.
Hasil
dari penelitian ini menunjukkan bahwa dalam proses identifikasi risiko pada
pekerjaan bekisting dan perancah dalam proyek Rumah Susun Tenaga Pendidik UGM,
digunakan metode Job Safety Analysis (JSA) dan Hazard Identification,
Risk Assessment, and Determining Control (HIRADC). Penelitian ini
mengidentifikasi tiga tingkat bahaya yang mengacu pada indeks/matriks risiko
sesuai dengan standar SNI IEC/ISO 31000:2016. Ketiga tingkatan bahaya tersebut
mencakup bahaya rendah, sedang, dan tinggi, dan penerapannya difokuskan pada
aktivitas fabrikasi, instalasi, dan pembongkaran. Temuan ini memberikan
pemahaman yang lebih jelas mengenai keragaman tingkat risiko dalam pekerjaan
bekisting dan perancah di lingkungan proyek konstruksi, serta berkontribusi
pada perancangan langkah-langkah pengendalian risiko yang lebih efektif dan
tepat.
In
the study of construction, formwork plays a pivotal role in shaping concrete
according to design specifications prior to its curing phase, involving
installation, fabrication, and subsequent removal. The inherent risks
associated with this process necessitate careful management. The primary
objective of this research is to assess the effectiveness of the Job Safety
Analysis (JSA) and Hazard Identification Risk Assessment and Determining
Control (HIRADC) methodologies in controlling the risks inherent in formwork operations
within the context of the educator's apartment building project at Gadjah Mada
University (UGM). This study is centered on the educator's apartment building
project at UGM, with the aim of comprehending the contributions of these
methods in mitigating risks and enhancing occupational safety. The anticipated
outcomes hold potential significance for the construction industry and
occupational safety by shedding new insights into the identification,
evaluation, and control of formwork-related risks, while concurrently
augmenting safety awareness among educators and practitioners, thereby
potentially reducing incidents in future construction endeavors.
The
research methodology employed encompasses the utilization of the Job Safety
Analysis (JSA) and Hazard Identification, Risk Assessment, and Determining
Control (HIRADC) methods to identify and evaluate occupational risks inherent
in formwork and scaffolding activities within the framework of the Educator's
Apartment Building project at UGM.
The
outcomes derived from this research reveal that in the process of risk
identification pertaining to formwork and scaffolding activities within the
Educator's Apartment Building project at UGM, the Job Safety Analysis (JSA) and
Hazard Identification, Risk Assessment, and Determining Control (HIRADC)
methodologies were employed. This study delineates the identification of three
levels of hazards referencing the risk index/matrix as stipulated by the SNI
IEC/ISO 31000:2016 standard. These three tiers encompass low, moderate, and
high hazards, with their application specifically tailored to fabrication,
installation, and dismantling activities. These findings furnish a clearer
comprehension of the diversified spectrum of risk levels entailed in formwork
and scaffolding operations within the construction project milieu, thereby
contributing to the formulation of more effective and precise risk control
measures.
Kata Kunci : Bekisting, Manajemen Risiko, K3