Analisis Produktivitas Alat Berat Drilling Rig Machine Pada Pekerjaan Pondasi Bore Pile Proyek Jalan Tol Jogja – Bawen Sta 70+520 dan Sta 72+275 Paket 1 Seksi 1
Ahmad Zulfan Rozaqtana, Dr. Devi Oktaviana Latif, S.T., M. Eng
2023 | Tugas Akhir | D4 TEKNIK PENGELOLAAN DAN PEMELIHARAAN INFRASTRUKTUR SIPIL
Penggunaan alat berat dalam
pelaksanaan pondasi Bore Pile sangat penting untuk mempermudah pekerjaan dalam
skala besar. Pemilihan jenis, ukuran, dan jumlah alat berat harus tepat guna.
Namun, proses pengeboran menggunakan alat berat Rotary Drilling Rig di lokasi elevated 3 dan elevated 2 memakan
waktu lama, menyebabkan hambatan pada pekerjaan lainnya. Dalam penelitian ini
akan dilakukan analisis produktivitas, faktor – faktor yang memengaruhui, dan
biaya pekerjaan pengeboran bore pile
berdasarkan pengamatan langsung dilapangan.
Penelitian dilakukan pada
proyek pembangunan jalan tol Jogja-Bawen Paket 1 seksi 1.Penelitian ini
dilakukan dengan mencatat aktivitas pekerjaan pengeboran bore pile penggunaan mesin rotary
drilling rig. Hasil pengamatan dianalisis untuk mendapatkan nilai
produktivitas, faktor – faktor yang memengaruhi, dan estimasi biaya pelaksanaan
dilapangan.
Hasil analisis menunjukkan bahwa nilai produktivitas pada P37 yaitu 7,28m/jam dan produktivitas pemasangan casing 5 casing/jam dengan estimasi biaya pelaksanaan pekerjaan pondasi bore pile yaitu Rp. 953.515.993,06, sedangkan nilai produktivitas pada P63A yaitu 4,78 m/jam dan produktivitas pemasangan casing 5 casing/jam dengan estimasi biaya pelaksanaan pekerjaan pondasi bore pile yaitu Rp. 1.438.907.395,61. Terdapat juga beberapa faktor memiliki pengaruh signifikan terhadap produktivitas mesin rotary drilling rig. Faktor-faktor tersebut antara lain karakteristik tanah, kondisi alat berat, pekerja, dan manajemen.
The
use of heavy equipment in carrying out Bore Pile foundations is very important
to facilitate work on a large scale. Selection of the type, size and number of
heavy equipment must be appropriate. However, the drilling process using Rotary
Drilling Rig heavy equipment at the elevated 3 and elevated 2 locations takes a
long time, causing obstacles to other work. In this study an analysis of
productivity, influencing factors, and the cost of bore pile drilling work will
be carried out based on direct field observations. The
research was conducted on the Jogja-Bawen Paket 1 toll road construction
project section 1. This research was conducted by recording bore pile drilling
work activities using a rotary drilling rig machine. Observations were analyzed
to obtain productivity values, influencing factors, and estimated costs for
field implementation. The
results of the analysis show that the productivity value at P37 is 7.28m/hour
and the casing installation productivity is 5 casing/hour with an estimated
cost of carrying out the bore pile foundation work of Rp. 953,515,993.06, while
the productivity value at P63A is 4.78 m/hour and casing installation
productivity is 5 casing/hour with an estimated cost of carrying out bore pile
foundation work of Rp. 1,438,907,395.61. There are also several factors that
have a significant influence on the productivity of the rotary drilling rig
machine. These factors include soil characteristics, condition of heavy
equipment, workers and management.
Kata Kunci : bore pile, rotary driliing rig, produktivitas, durasi