Studi Kelayakan Investasi Rencana Pengembangan Pembangkit Listrik Tenaga Panas Bumi: unit II Dieng Jawa Tengah

Saroso, Bambang Joko, Dr. Hardo Basuki, M.Soc.Sc., Ak.

2008 | Skripsi | S1 Extention - Accounting

Daerah penelitian terletak di lapangan panasbumi Dieng, Propinsi Jawa Tengah. Lapangan panasbumi Dieng merupakan wilayah kerja ke-6 pertamina yang dalam pengelolaannya diserahkan kepada PT Geo Dipa Energi. PT Geo Dipa Energi sebagai anak perusahaan Pertamina telah melakukan penyelidikan Geoscience rinci, pengeboran eksplorasi hingga pengeboran eksploitasi. Cadangan energi panasbumi yang terkandung di lapangan Dieng adalah sebesar + 400MW. Sebagai tahap awal pengembangan PT Geo Dipa Energy telah berhasil mengoperasikan Unit I Dieng berkapasitas 60 MW sejak tahun 2002 dan direncanakan akan dibangun Unit II Dieng dengan kapasitas 1 x 60 MW mulai tahun 2008. Berdasarkan kajian teknis telah ditentukan jenis dan letak turbin serta sistem power plant yang digunakan. Sistem power plant yang digunakan adalah tipe condesing dengan jenis turbin single flash. Dari hasil kajian finansial di peroleh payback period 10,9 tahun, net present value +US$33,16 juta dengan internal rate of return 14,41% sehingga dinyatakan proyek tersebut layak dilaksanakan. Kata kunci : Energi panasbumi, penilaian kelayakan investasi.

The research location is in Dieng geothermal field, Central Java Province. Dieng geothermal field is the 6th working area of Pertamina of which management is given to Geo Dipa Energi Ltd. Geo Dipa Energi Ltd as a company below Pertamina authorization has run a detailed geo-scientific research from exploration drilling until exploitation drilling. Geothermal reserves in this field are about 400MW. As the first development step, Geo Dipa Energi Ltd. has successfully operated the First Unit Dieng which has the capacity of 60 MW since 2002 and they have planned to build the Second Unit Dieng which has the capacity of 1 x 60 MW starting from 2008. Based on technical studies have been found the type and location of turbine and power plant system which are going to be used. The power plant system which will be used is condensing type with the single flash type turbine.



From the result of financial calculation a payback period of 10.9 years, a net present value of about US$ 33.16 million with an internal rate of return of 14.41% are obtained so it is stated that this project is feasible to do. Keyword: Geothermal, investment feasibility assessment

Kata Kunci : kelayakan Investasi; Pengembangan Pembangkit Listrik; Studi Kelayakan